Timeline

Project Progamme – Preliminary Stages 1 and 2


Task Dates
Preliminary Design. estimates of cost- 10 weeks 8th May- 10th July 2018
Engage Sub-consultants for input into Preliminary Design 10th May- 10th July 2018
Resource Consent Application 8th May - 10th July 2018
Approvals/ Cardinal/ Rome submission 13th July 2018
Contract Documentation 16 weeks 16th July - 12th November 2018
Tender Period - 3 weeks 13th November- 4th December 2018
Approval / Acceptance- 2 weeks 5th December - 17th December 2018
Construction-12 months January 2019 - December 2019